A. The purchasing director shall issue a written decision within 14 days after a protest has been filed under MCC 3.65.180. The decision of the purchasing director shall contain the basis for the decision and a statement that the decision shall be final and binding on the parties.

1. Such decision shall be delivered to the appellant by certified U.S. Mail or by any other method that provides evidence of receipt.

B. If the purchasing director fails to issue a decision within the time limits set forth in this chapter, the interested party may proceed as if the purchasing director had issued an adverse decision. [Ord. 18-09 § 1; Res. 18-24; Code 2004 § 3-243.]